KSEB Info Portal
Thursday, August 22, 2024
Free Electricity for Essential Air Bed, Suction Device and Oxygen Concentrator |KSEB
Sunday, August 18, 2024
Procedures for Connecting Roof Top Solar Plants in KSEB Ltd|KSEB On-Grid Solar Connectivity|Forms and Procedures
According to the supply voltage given to the customer, the capacity of the plants that can be installed is given below.
Volt |
KWp |
240V-Single Phase |
1-5 |
415V-Three Phase |
Upto 100 |
11kV |
Upto 1000 |
While installing solar plants, KSEB A bi-directional meter that measures the difference between the electricity used from the grid (import) and the electricity sent to the grid (export) and a solar meter that measures the electricity generated by the solar plant should be installed. They can be purchased by the customer on their own. KSEB The prevailing monthly rent is applicable at the time of installation of meters. The applicant should inform himself in advance for testing the meters he will purchase on his own.
The net reading (export-import surplus) on the bi-directional meter shall be used for billing. When the import is over, the consumer will be billed at the prevailing rate for the surplus power. However, when the shipment is retained, the customer does not have to pay. And surplus electricity can be used next month. This may continue in the coming months. Finally, if there is an export surplus in meters on 30th September every year, that much electricity will be sold to KSEB. Price for purchase consideration will give Thus the period from October 1 to September 30 is called the settlement period. As determined by the Regulatory Commission, KSEB The price will be based on the average purchase price of electricity purchased from abroad.
Multiple consumer premises solar power systems can be connected to the power distribution network, one per consumer premises.Electricity generated at one location can be used elsewhere by the same customer. The following conditions apply to it.
Note:
As per circular issued by KSEB dated 12/04/22 testing procedures of Roof top solar plants have been eased. Such a circular has been issued considering the rapid spread of solar plants. According to this,
1. Roof top solar plants with capacity of 50 kilowatt peak (kWp) and below will no longer require grid connectivity testing by KSEB.
2. Inverters used in such solar plants before providing grid connectivity , Electrical section offices should ensure that IS certified and anti-islanding protection is provided.
3. Net meter and renewable meter (solar meter) should be placed so as to enable reading (essentially eliminating the need to place both next to each other)
4. Electrical Inspectorate testing / energization sanction will be applicable only for plants having capacity of 10 kilowatt(kWp) and above.
5. Inspectorate scheme approval is not required for plants up to 30 KW peak capacity. But the Energization Certificate is applicable for plants with peak capacity of 10 to 30 KW.
6. It is the responsibility of the Electrical Section Office to provide grid connectivity within 15 days after the customer submits the completion report of the plants with a capacity of up to 100 kilowatt peak.
7. 10% of new plants up to 50 KW under each Section Office will be subjected to KSEB testing. Renewable Energy and Energy Savings will take appropriate action if such testing fails.
* This is applicable to both those who are covered by the solar scheme and those who are not.
Thursday, August 15, 2024
KSEB Single Phase to Three Phase Conversion |Application Form |Fee's and Procedures 2024
KSEB Meter Shifting ,Tariff Change and Load Change |Application Form |Step by Step Process 2024
Cost of KSEB Service Connection with Posts w. e.f 08.02.2024|KSEB Over Head (OH) Connection Charges |KSEB ECSC
Thursday, August 8, 2024
Free service connection up to 250 meters for BPL households|KSEB Free Service Connection |KSEB Ltd
Sunday, July 14, 2024
What is ACD in KSEB Bill?|ACD|KSEB
KSEB Weather Proof(WP) Service Connection Charges w.e.f 08.02.2024|KSEB Connection Charges with Service Wire 2024
- Domestic -₹300 per kW (1Watts -1000Watts =1kW1001 Watts -2000 Watts =2kW and so on).
- Construction Purpose, Commercial,Religious -₹1000 per kW
- Agriculture,Anganvadi -₹200 per kW
- Industrial-₹500 per kW
- Single Phase -₹2258/-
- Three Phase -₹5478/-
Saturday, September 9, 2023
KSEB HRIS|HOW TO USE IT WITHOUT ORUMANET?|KSEB SSO PORTAL
This is a web portal for KSEB Employees to access their service details from anywhere .It also deals with the internal matters in KSEB Ltd.
5.Enter OTP received.Then you can Change your password.
6.After logging in you can access your HRIS.
Contact Form
Featured Post
Cost of KSEB Service Connection with Posts w. e.f 08.02.2024|KSEB Over Head (OH) Connection Charges |KSEB ECSC
In this article, let's know about revised KSEB ECSC (Estimate Cost for Service Connection ) rates w.e.f 08.02.2024.There is no change in...
