KSEB Meter Shifting ,Tariff Change and Load Change |Application Form |Step by Step Process 2024


Let us see what is the step by step procedure of Load Change ,Tariff Change and Meter Shifting in KSEB . An application regarding a service connection e.g. revising connected load, phase conversion, tariff change, billing disputes etc. will normally be processed only if the registered consumer is the applicant.Also , ensure thatall the electrical installations are done by a licensed Electrical Contractor. 

1.Meter Shifting ,Tariff Change and Load Change
If you are re-build your house or complex(for Construction Purpose)you have to apply for these three.Also after the completion of works you need to do the procedures once again.
At first you must make the arrangements to shift the meter to a safe place with the help of a licensed contractor .In this regard, proper Earthing and Protection of Metering Equipment and other Saftety measures like E.L.C.B/R.C.C.B are very essential.
For the Tariff change ,the consumer premises must the requirements of proposed Tariff.
The load calculation should match with the existing installations.Incorrect load may lead to penal bills later.
 
Application Forms(See Downloads )
 
1.For Load Change.
2.For Tariff Change and Meter Shifting.
 
Supporting Documets
 
1.Identity Proof
2.Test Report/Completion Certificate.
3.Sketch of Installation.

After submitting the Application ,your details are verified by a field staff.
Fees and ACD(Including GST(18%)).
 
1.Application Fee-Rs.58/-
 
2.Meter Shifting Fee-Rs.1073/-(Single Phase)

3.ACD-Rs.300/- for 1000 Watts (Domestic).

If your existing CD is Rs.850 and you need to enhance your connected load from 2000 watts to 4500 watts, then you have to pay Rs.650 as ACD.
 
Other Purposes and  required CD per 1000 watts.
Commercial -Rs.1000
Agriculture -Rs. 200
Construction-Rs.1000
Industrial -Rs.500
Temple/Mosque/Church -Rs.1000

 
The Forms can be used for single purposes and Consumer can fill the application based on their needs.The difference in fees is as follows.
 
Ø Tariff Change and Load Change
 
1.Application Fee-Rs.58/-
2 ACD-Rs.300/- for 1000 Watts (Domestic )and Rs.1000/-(Other).
 
Ø Meter Shifting
 
1.Application Fee-Rs.41/-
2.Meter Shifting Fee-Rs.1073/-
 
Ø Load Change
 
1.Application Fee-Rs.58/-
2 ACD-Rs.300/- for 1000 Watts (Domestic ).

Ø Tariff Change
 
1.Application Fee-Rs.41/-
 
Some Common Tariff and Purposes.

LT-1A-Domestic
LT-4A-Industrial/Drinking Water Projects.
LT-7A-Commercial
LT-7B-Commercial(Small Shop/Bunk)
LT-6F-Construction/Mobile Towers/Un-aided Schools
LT-6A-Mosque/Temple/Church/Govt or Aided School.
LT-6D-Anganvadi
LT-6G-Medical Lab
LT-5B-Farms
LT-5A-Agriculture
LT-6C-Bank
LT-10- Electric Charging Stations(New)

No comments:

Post a Comment

Contact Form

Name

Email *

Message *

Featured Post

Cost of KSEB Service Connection with Posts w. e.f 08.02.2024|KSEB Over Head (OH) Connection Charges |KSEB ECSC

In this article, let's know about revised KSEB ECSC (Estimate Cost for Service Connection ) rates w.e.f 08.02.2024.There is no change in...