Sunday, August 18, 2024

Procedures for Connecting Roof Top Solar Plants in KSEB Ltd|KSEB On-Grid Solar Connectivity|Forms and Procedures

Grid Interactive Solar Plants (GRID Interactive Solar Plants) which can be connected to KSEB's power distribution network are now available to KSEB. Permission is granted. In this regard, they are given permission as per the rules issued by the Kerala State Electricity Regulatory Commission on 30 June 2014.  This permission is granted to all customers of KSEB Ltd. And such stations can be installed only in the premises (Consumer Premises) specified in the existing service connection agreement with the customer. Plants with a capacity of 1 kWt to 1MW are permitted to be connected to the power distribution network.

 According to the supply voltage given to the customer, the capacity of the plants that can be installed is given below.

          Volt

       KWp

240V-Single Phase

1-5

415V-Three Phase

Upto 100

11kV

Upto 1000

 While installing solar plants, KSEB A bi-directional meter that measures the difference between the electricity used from the grid (import) and the electricity sent to the grid (export) and a solar meter that measures the electricity generated by the solar plant should be installed. They can be purchased by the customer on their own. KSEB The prevailing monthly rent is applicable at the time of installation of meters. The applicant should inform himself in advance for testing the meters he will purchase on his own.

The net reading (export-import surplus) on the bi-directional meter shall be used for billing. When the import is over, the consumer will be billed at the prevailing rate for the surplus power. However, when the shipment is retained, the customer does not have to pay. And surplus electricity can be used next month. This may continue in the coming months. Finally, if there is an export surplus in meters on 30th September every year, that much electricity will be sold to KSEB. Price for purchase consideration will give Thus the period from October 1 to September 30 is called the settlement period. As determined by the Regulatory Commission, KSEB The price will be based on the average purchase price of electricity purchased from abroad.

Multiple consumer premises solar power systems can be connected to the power distribution network, one per consumer premises.Electricity generated at one location can be used elsewhere by the same customer. The following conditions apply to it. 

(1) Connection agreement at those locations should be in own name,
(2) Export surplus at generation location (after deducting consumption at consumer premises generating solar energy) should be 500 units or more per month, 
(3) Priority of locations should be intimated in advance along with application, 
(4) 5% of export surplus less for distribution loss and other expenses.

T.O.D. (Time-of-day) based on the usage of solar power generated by consumers in (1) first peak period from 6 AM to 6 PM (Normal Period), (2) if there is surplus, then from 6 PM to 10 PM (Peak Period),( 3) Again if there is surplus it is from 10 pm to 6 am will be considered used during (off-peak period).
 
Design, quality of construction, installation and safe operation of solar power plants shall be the sole responsibility of the customer. The plants are to be installed and operated as per the Central Electricity Authority's regulation "Technical Standards of Connectivity for Distributed Generation Resources", 2013.
KSEB in emergencies. If requested, the solar system shall be allowed to be inspected.

 Procedures for approval

1]Solar Power Plants KSEB For connection to the network of, the application in Annexure-1 should be filled and submitted to the Electrical Section Offices at the respective location. 
Before submitting the application, you should verify your connected load is enough for submitting Anexxure 1. In the case of single phase domestic consumer upto 5kWp can be installed without considering connected load. But in other tariffs, connected load should be match with your requirement.
If you wish to install a 3 kWp plant in your shop its connected load should be greater than or equal to 3000 Watts.
1000 as application fee should be paid in cash or by bank demand draft drawn in the name of Assistant Engineer.
Amount to Pay with GST-1180/-
2]The applicant will be informed through a Feasibility Certificate within 15 days after verifying whether the plant can be connected to the distribution network. It is valid for 30 days. Intending to install the station
The maximum solar capacity that can be connected on that feeder is 80% of the minimum load on the feeder.
Relationship between DTR Capacity and Feasiblity can be explained as follows :
If Capacity of DTR is 100 kVA. If power factor is assumed as 0.9 total kW=90. Then 75 % of total load is 67 kw will be the maximum allowable solar plant capacity in that DTR.If the capacity is over, enhancement of DTR is necessary.
Similarly in the case of other DTRs.
160 kVA-108 kW
250 kVA-169 kW
315 kVA- 213 kW
The availability of DTR for solar installation can be check using the link.
3]Then within 30 days from the date of prospectus the applicant should register in the application form in Annexure-2. The registration fee is Rs.1000 per kilowatt capacity of the plant. (Fractions are rounded to the nearest whole number)
i.e, registration fees of the scheme for installation of solar energy
system should be paid within 30 days. If you fail to do so within 30 days from the date of issue of this certificate you will
loose your priority.
Please submit the following documents along with application for registration
1.Scheme for installation of the solar energy system (Single Line diagram)
2.Technical specifications as well as other particulars of the grid-tied inverter, manually
operated isolating switch,renewable energy meter and net meter
3.Type Test Certificates for MCB,ELCB, fuse, inverter,etc issued by the laboratories
accredited by the National Accreditation Board For Testing and Calibration Laboratories
(NABL) or by such other institutions at international level for the testing and calibration of
electrical equipment
Registration Fee with GST 
1 kW -1180
2 kW- 2360
3 kW-3540
4 kW- 4720
5 kW- 5900
6 kW-7080
7 kW-8260
8 kW-9440
9 kW-10620
10 kW- 11800

If 52kW -61360

4]Consumers who want to purchase energy meters on their own should contact KSEB. After purchasing the specified types of meters, they should be reported to the concerned section office for testing.Others wise they can approach the Meter Testing authority under Electrical Inspctorate.

5]KSEB to test and install Net Meter and Solar Meter purchased by consumers. is liable.

6]The station shall be installed by authorized wireman / supervisor / contractor within six months thereafter. After that permission (Energization Certificate) should be obtained from the concerned Electrical Inspector.
As per order from Elecctrical Inspectorate,a valid B Calss Contractor can only install such plants.

7]Application may be made for testing the plant as per Annexure-3 including the above permit and technical information of the installed plant and type-test report issued by its manufacturer. Then the station K.S.E.B. Will test. The net-meter agreement should be signed within 15 days thereafter. After that, meters will be installed and the station will be connected to the network within 7 days. After that the plant can be operated.

Nowadays List of Documents required while submitting Anexxure 2and 3.

1 Single Line Diagram (Sketch (of Plant 
2 Test Cum Completion Report(B Class Contractor )
3 Test Certificates of Panel, Inverter, Breakers 
4 Letter of Undertaking(Regarding replacement of inverter is it fails in PQ testing )
6 Meter Test Report(Solar Meter also should have TOD facility )
7 Net Meter Agreement 
8 Request for Net Meter

Note:

As per circular issued by KSEB dated 12/04/22 testing procedures of Roof top solar plants have been eased. Such a circular has been issued considering the rapid spread of solar plants. According to this,
 1. Roof top solar plants with capacity of 50 kilowatt peak (kWp) and below will no longer require grid connectivity testing by KSEB.

2. Inverters used in such solar plants before providing grid connectivity , Electrical section offices should ensure that IS certified and anti-islanding protection is provided.

3. Net meter and renewable meter (solar meter) should be placed so as to enable reading (essentially eliminating the need to place both next to each other)

4. Electrical Inspectorate testing / energization sanction will be applicable only for plants having capacity of 10 kilowatt(kWp) and above.

5. Inspectorate scheme approval is not required for plants up to 30 KW peak capacity. But the Energization Certificate is applicable for plants with peak capacity of 10 to 30 KW.

6. It is the responsibility of the Electrical Section Office to provide grid connectivity within 15 days after the customer submits the completion report of the plants with a capacity of up to 100 kilowatt peak.

7. 10% of new plants up to 50 KW under each Section Office will be subjected to KSEB testing. Renewable Energy and Energy Savings will take appropriate action if such testing fails.

* This is applicable to both those who are covered by the solar scheme and those who are not.

No comments:

Post a Comment

Contact Form

Name

Email *

Message *

Featured Post

Cost of KSEB Service Connection with Posts w. e.f 08.02.2024|KSEB Over Head (OH) Connection Charges |KSEB ECSC

In this article, let's know about revised KSEB ECSC (Estimate Cost for Service Connection ) rates w.e.f 08.02.2024.There is no change in...