✅ Eligibility

  • Premises must lie within 35 m of an existing electric post.

  • Connection will be through a service wire.

  • New connections are granted based on priority order.


💰 Fees & Charges (to be paid at the Electrical Section)

ChargeAmountNotes
Application Fee (AF)₹ 50Same whether application is online or offline
Cash Deposit (CD)Depends on connected load (kW)Rate differs by usage category:
Domestic: ₹ 300 / kW
 Construction / Commercial / Religious: ₹ 1,000 / kW
 Agriculture / Anganvadi: ₹ 200 / kW
 Industrial: ₹ 500 / kW
ECSC (Estimate Cost for Service Connection)Single Phase: ₹ 1,914
Three Phase: ₹ 4,642
Flat rates depending on whether single or three phase connection


If your Connected Load is 3756 Watts in Domestic tharif, You have to pay 4X300= ₹1200
ECSC=₹1914
Total=₹3114


 